According to Architectural Barriers Administrative Rule 68.52, the owner of a building or facility subject to §469.101 of the Architectural Barriers Act shall obtain an inspection from a registered accessibility specialist not later than the first anniversary of the completion of construction.
TAS TEXAS. LLC's TAS Site Inspection Consulting includes the Site Inspection, Inspection Worksheet, discussion of items noted on the Inspection Worksheet, discussion and explanation of TAS requirements and current AB Interpretations.
Owner's Request
According to TDLR’s 2018 RAS Procedures, a written statement requesting the TAS Inspection is required. The Inspection Request must be completed by the an employee of the Building/Facility Owner as entered on the TDLR Project Registration or the Owner’s Designated Agent as identified on the Owner Agent Designation Form. TDLR would accept a statement in an email as valid for this purpose. TDLR will also accept a completed TDLR Request for Inspection Form signed by the Owner or the Owner’s Designated Agent.
Owner Agent Designation Form
If the Inspection Request is completed by the Owner’s Designated Agent, TDLR requires a TDLR Owner Agent Designation Form signed by an employee of the Building Owner.
Contact Information
In addition to the Owner’s or Designated Agent’s written/email request, we also require the following contact information:
Inspection Request
Site Contact
An individual's name, company name, company address, phone, and email for the person who should be called to schedule the inspection. Typically, this is the person who can meet the inspector at the site and ensure that the inspector has access to all areas contained in the scope of work for the project.
Billing Contact
An individual's name, company name, company address, phone, and email for the person who should receive and process the inspection invoice.
Owner Agent Designation Form
Owner Agent Designation Form - Completed by the Building/Facility Owner or an Employee of Building/Facility Owner [Company holding Title] ONLY if the Owner wishes to designate an Agent (who is not an employee of the Building/Facility Owner) to make decisions regarding TAS/Accessibility.
Inspection Process
Submit Forms
​
​
Conduct Inspection
Inspection Report
Inspection Response Corrective Modifications